03/29/01
MEMORIAL LIBRARY
90% CONSTRUCTION DOCUMENT
Project Area 62479 Square Feet
96 5130
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
486,197 |
6.20% |
7.78 |
|
|
02 |
Site Work |
659,046 |
8.41% |
10.55 |
|
|
03 |
Concrete |
457,051 |
5.83% |
7.32 |
|
|
04 |
Masonry |
539,479 |
6.88% |
8.63 |
|
|
05 |
Metals |
900,742 |
11.49% |
14.42 |
|
|
06 |
Wood & Plastics |
561,195 |
7.16% |
8.98 |
|
|
07 |
Moisture-Thermal Control |
566,264 |
7.22% |
9.06 |
|
|
08 |
Doors, Windows & Glass |
648,460 |
8.27% |
10.38 |
|
|
09 |
Finishes |
896,003 |
11.43% |
14.34 |
|
|
10 |
Specialties |
44,869 |
0.57% |
0.72 |
|
|
11 |
Equipment |
12,000 |
0.15% |
0.19 |
|
|
12 |
Furnishings |
17,781 |
0.23% |
0.28 |
|
|
13 |
Special Construction |
75,000 |
0.96% |
1.20 |
|
|
14 |
Conveying Systems |
105,000 |
1.34% |
1.68 |
|
|
15 |
Mechanical |
1,226,603 |
15.65% |
19.63 |
|
|
16 |
Electrical |
642,628 |
8.20% |
10.29 |
|
|
|
Job total |
|
$7,838,319 |
100.00% |
$125.46 |
|
|
Profit |
10% |
$783,832 |
|
|
|
|
Bond |
1% |
$78,383 |
|
|
|
|
Contingency |
10% |
$783,832 |
|
|
|
|
Grand Total |
|
$9,484,366 |
|
$151.80 |