03/29/01
PUBLIC LIBRARY
DESIGN DEVELOPMENT ESTIMATE
Project Area 30237 Square Feet
00 0750
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
275,688 |
9.82% |
9.12 |
|
|
02 |
Site Work |
419,897 |
14.95% |
13.89 |
|
|
03 |
Concrete |
145,418 |
5.18% |
4.81 |
|
|
04 |
Masonry |
214,536 |
7.64% |
7.10 |
|
|
05 |
Metals |
82,045 |
2.92% |
2.71 |
|
|
06 |
Wood & Plastics |
211,300 |
7.52% |
6.99 |
|
|
07 |
Moisture-Thermal Control |
154,464 |
5.50% |
5.11 |
|
|
08 |
Doors, Windows & Glass |
237,935 |
8.47% |
7.87 |
|
|
09 |
Finishes |
288,592 |
10.27% |
9.54 |
|
|
10 |
Specialties |
12,060 |
0.43% |
0.40 |
|
|
11 |
Equipment |
5,000 |
0.18% |
0.17 |
|
|
12 |
Furnishings |
14,417 |
0.51% |
0.48 |
|
|
13 |
Special Construction |
74,880 |
2.67% |
2.48 |
|
|
14 |
Conveying Systems |
60,000 |
2.14% |
1.98 |
|
|
15 |
Mechanical |
375,574 |
13.37% |
12.42 |
|
|
16 |
Electrical |
237,011 |
8.44% |
7.84 |
|
|
|
Job total |
|
$2,808,820 |
100.00 % |
$92.89 |
|
|
Profit |
10% |
$280,882 |
|
|
|
|
Bond |
1% |
$28,088 |
|
|
|
|
Contingency |
10% |
$280,882 |
|
|
|
|
Grand Total |
|
$3,398,672 |
|
$112.40 |