03/29/01
ELDERLY HOUSING/
ASSISTED LIVING – 6 Story
CONSTRUCTION DOCUMENT
Project Area 64560 Square Feet
97 1400
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
298,676 |
4.98 |
4.63 |
|
|
02 |
Site Work |
181,951 |
3.04 |
2.82 |
|
|
03 |
Concrete |
511,951 |
8.54 |
7.93 |
|
|
04 |
Masonry |
584,288 |
9.75 |
9.05 |
|
|
05 |
Metals |
181,767 |
3.03 |
2.82 |
|
|
06 |
Wood & Plastics |
379,209 |
6.33 |
5.87 |
|
|
07 |
Moisture-Thermal Control |
295,007 |
4.92 |
4.57 |
|
|
08 |
Doors, Windows & Glass |
437,192 |
7.30 |
6.77 |
|
|
09 |
Finishes |
750,945 |
12.53 |
11.63 |
|
|
10 |
Specialties |
34,038 |
0.57 |
0.53 |
|
|
11 |
Equipment |
105,350 |
1.76 |
1.63 |
|
|
12 |
Furnishings |
2,577 |
0.04 |
0.04 |
|
|
13 |
Special Construction |
15,395 |
0.26 |
0.24 |
|
|
14 |
Conveying Systems |
168,000 |
2.80 |
2.60 |
|
|
15 |
Mechanical |
1,238,997 |
20.68 |
19.19 |
|
|
16 |
Electrical |
806,840 |
13.46 |
12.50 |
|
|
|
Job total |
|
$5,992,185 |
100.00% |
$92.82 |
|
|
Profit |
5% |
$299,609 |
|
|
|
|
Bond |
1% |
$59,922 |
|
|
|
|
Contingency |
2% |
$119,844 |
|
|
|
|
Grand Total |
|
$6,471,560 |
|
$100.24 |