03/29/01
ART MUSEUM RENOVATION
CONSTRUCTION DOCUMENT
Project Area 1912 Square Feet
95 0220
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
51,744 |
12.39% |
27.06 |
|
|
02 |
Site Work |
85,512 |
20.47% |
44.72 |
|
|
03 |
Concrete |
20,152 |
4.83% |
10.54 |
|
|
04 |
Masonry |
40,015 |
9.58% |
20.93 |
|
|
05 |
Metals |
61,027 |
14.61% |
31.92 |
|
|
06 |
Wood & Plastics |
12,420 |
2.97% |
6.50 |
|
|
07 |
Moisture-Thermal Control |
13,031 |
3.12% |
6.82 |
|
|
08 |
Doors, Windows & Glass |
31,263 |
7.49% |
16.35 |
|
|
09 |
Finishes |
47,043 |
11.26% |
24.60 |
|
|
15 |
Mechanical |
30,592 |
7.32% |
16.00 |
|
|
16 |
Electrical |
24,856 |
5.95% |
13.00 |
|
|
|
Job total |
|
$417,656 |
100.00 % |
$218.44 |
|
|
Profit |
10% |
$41,766 |
|
|
|
|
Bond |
1% |
$4,177 |
|
|
|
|
Contingency |
10% |
$41,766 |
|
|
|
|
Grand Total |
|
$505,363 |
|
$264.31 |