03/29/01
UNIVERSITY FOUNDATION BUILDING
75% CONSTRUCTION DOCUMENT
Project Area 10648 Square Feet
99 3510
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
|
01 |
General Requirements |
62,500 |
3.81% |
5.87 |
|
|
|
02 |
Site Work |
297,446 |
18.13% |
27.93 |
|
|
|
03 |
Concrete |
69,214 |
4.22% |
6.50 |
|
|
|
04 |
Masonry |
97,778 |
5.96% |
9.18 |
|
|
|
05 |
Metals |
24,305 |
1.48% |
2.28 |
|
|
|
06 |
Wood & Plastics |
339,405 |
20.69% |
31.88 |
|
|
|
07 |
Moisture-Thermal Control |
66,124 |
4.03% |
6.21 |
|
|
|
08 |
Doors, Windows & Glass |
107,712 |
6.57% |
10.12 |
|
|
|
09 |
Finishes |
185,158 |
11.29% |
17.39 |
|
|
|
10 |
Specialties |
4,071 |
0.25% |
0.38 |
|
|
|
11 |
Equipment |
9,000 |
0.55% |
0.85 |
|
|
|
14 |
Conveying Systems |
60,000 |
3.66% |
5.63 |
|
|
|
15 |
Mechanical |
189,984 |
11.58% |
17.84 |
|
|
|
16 |
Electrical |
127,903 |
7.80% |
12.01 |
|
|
|
|
Job total |
|
$1,640,601 |
100.00% |
$154.08 |
|
|
|
Profit |
10% |
$164,060 |
|
|
|
|
|
Bond |
1% |
$16,406 |
|
|
|
|
|
Contingency |
10% |
$164,060 |
|
|
|
|
|
Grand Total |
|
$1,985,127 |
|
$186.43 |
|