03/29/01
COLLEGE SCIENCE LAB BUILDING
CONSTRUCTION DOCUMENT ESTIMATE
Project Area 11241 Square Feet
96 5920
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
|
01 |
General Requirements |
136,719 |
4.42% |
12.16 |
|
|
|
02 |
Site Work |
508,539 |
16.44% |
45.24 |
|
|
|
03 |
Concrete |
329,141 |
10.64% |
29.28 |
|
|
|
04 |
Masonry |
270,991 |
8.76% |
24.11 |
|
|
|
05 |
Metals |
34,622 |
1.12% |
3.08 |
|
|
|
06 |
Wood & Plastics |
55,502 |
1.79% |
4.94 |
|
|
|
07 |
Moisture-Thermal Control |
71,899 |
2.32% |
6.40 |
|
|
|
08 |
Doors, Windows & Glass |
134,751 |
4.36% |
11.99 |
|
|
|
09 |
Finishes |
126,287 |
4.08% |
11.23 |
|
|
|
10 |
Specialties |
1,945 |
0.06% |
0.17 |
|
|
|
13 |
Special Construction |
46,842 |
1.51% |
4.17 |
|
|
|
14 |
Conveying Systems |
40,000 |
1.29% |
3.56 |
|
|
|
15 |
Mechanical |
1,046,241 |
33.82% |
93.07 |
|
|
|
16 |
Electrical |
289,980 |
9.37% |
25.80 |
|
|
|
|
Job total |
|
$3,093,459 |
100.00% |
$275.19 |
|
|
|
Profit |
6% |
$185,608 |
|
|
|
|
|
Bond |
1% |
$30,935 |
|
|
|
|
|
Contingency |
2.5% |
$77,336 |
|
|
|
|
|
Grand Total |
|
$3,387,338 |
|
$301.34 |
|