03/29/01
MIDDLE SCHOOL
CONSTRUCTION DOCUMENT
Project Area 180000 Square Feet
95
0710
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|||
|
01 |
General Requirements |
1,098,540 |
6.38% |
6.10 |
|||
|
02 |
Site Work |
1,427,914 |
8.29% |
7.93 |
|||
|
03 |
Concrete |
1,039,801 |
6.04% |
5.78 |
|||
|
04 |
Masonry |
2,559,634 |
14.86% |
14.22 |
|||
|
05 |
Metals |
1,230,239 |
7.14% |
6.83 |
|||
|
06 |
Wood & Plastics |
367,958 |
2.14% |
2.04 |
|||
|
07 |
Moisture-Thermal Control |
708,003 |
4.11% |
3.93 |
|||
|
08 |
Doors, Windows & Glass |
742,837 |
4.31% |
4.13 |
|||
|
09 |
Finishes |
1,342,441 |
7.80% |
7.46 |
|||
|
10 |
Specialties |
433,176 |
2.52% |
2.41 |
|||
|
11 |
Equipment |
563,000 |
3.27% |
3.13 |
|||
|
12 |
Furnishings |
116,881 |
0.68% |
0.65 |
|||
|
14 |
Conveying Systems |
63,000 |
0.37% |
0.35 |
|||
|
15 |
Mechanical |
3,684,722 |
21.40% |
20.47 |
|||
|
16 |
Electrical |
1,842,102 |
10.70% |
10.23 |
|||
|
|
Job total |
|
$17,220,248 |
100.00% |
$95.67 |
||
|
|
Profit |
5% |
$861,012 |
|
|
||
|
|
Bond |
0.8% |
$137,762 |
|
|
||
|
|
Contingency |
2.5% |
$430,506 |
|
|
||
|
|
Grand Total |
|
$18,649,529 |
|
$103.61 |
||