03/29/01
ELEMENTARY SCHOOL
90%CONSTRUCTION DOCUMENT
Project Area 73168 Square Feet
96 8260
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
|
01 |
General Requirements |
422,494 |
6.27% |
5.77 |
|
|
|
02 |
Site Work |
920,388 |
13.66% |
12.58 |
|
|
|
03 |
Concrete |
386,103 |
5.73% |
5.28 |
|
|
|
04 |
Masonry |
1,035,808 |
15.37% |
14.16 |
|
|
|
05 |
Metals |
247,389 |
3.67% |
3.38 |
|
|
|
06 |
Wood & Plastics |
209,927 |
3.12% |
2.87 |
|
|
|
07 |
Moisture-Thermal Control |
381,926 |
5.67% |
5.22 |
|
|
|
08 |
Doors, Windows & Glass |
398,609 |
5.92% |
5.45 |
|
|
|
09 |
Finishes |
476,152 |
7.07% |
6.51 |
|
|
|
10 |
Specialties |
118,548 |
1.76% |
1.62 |
|
|
|
11 |
Equipment |
149,500 |
2.22% |
2.04 |
|
|
|
12 |
Furnishings |
27,441 |
0.41% |
0.38 |
|
|
|
13 |
Special Construction |
20,000 |
0.30% |
0.27 |
|
|
|
14 |
Conveying Systems |
10,000 |
0.15% |
0.14 |
|
|
|
15 |
Mechanical |
972,163 |
14.43% |
13.29 |
|
|
|
16 |
Electrical |
962,449 |
14.28% |
13.15 |
|
|
|
|
Job total |
|
$6,738,896 |
100.00% |
$92.10 |
|
|
|
Profit |
5% |
$336,945 |
|
|
|
|
|
Bond |
1% |
$67,389 |
|
|
|
|
|
Contingency |
10% |
$673,890 |
|
|
|
|
|
Grand Total |
|
$7,817,119 |
|
$106.84 |
|