03/29/01
HOSPITAL REHABILITATION CENTER
CONSTRUCTION DOCUMENT NAME
Project Area 232472 Square Feet
92 1300
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|||
|
01 |
General Requirements |
3,630,731 |
9.04% |
15.62 |
|||
|
02 |
Site Work |
2,159,270 |
5.37% |
9.29 |
|||
|
03 |
Concrete |
5,387,441 |
13.41% |
23.17 |
|||
|
04 |
Masonry |
3,769,010 |
9.38% |
16.21 |
|||
|
05 |
Metals |
1,382,318 |
3.44% |
5.95 |
|||
|
06 |
Wood & Plastics |
1,649,422 |
4.10% |
7.10 |
|||
|
07 |
Moisture-Thermal Control |
1,126,935 |
2.80% |
4.85 |
|||
|
08 |
Doors, Windows & Glass |
2,282,952 |
5.68% |
9.82 |
|||
|
09 |
Finishes |
3,800,139 |
9.46% |
16.35 |
|||
|
10 |
Specialties |
494,340 |
1.23% |
2.13 |
|||
|
11 |
Equipment |
756,045 |
1.88% |
3.25 |
|||
|
12 |
Furnishings |
216,850 |
0.54% |
0.93 |
|||
|
13 |
Special Construction |
30,241 |
0.08% |
0.13 |
|||
|
14 |
Conveying Systems |
1,280,850 |
3.19% |
5.51 |
|||
|
15 |
Mechanical |
8,185,520 |
20.37% |
35.21 |
|||
|
16 |
Electrical |
4,029,382 |
10.03% |
17.33 |
|||
|
|
Job total |
|
$40,181,445 |
100.00% |
$172.84 |
||
|
|
Profit |
10% |
$4,018,145 |
|
|
||
|
|
Bond |
1% |
$401,814 |
|
|
||
|
|
Contingency |
5% |
$2,009,072 |
|
|
||
|
|
Grand Total |
|
$46,610,476 |
|
$200.50 |
||