03/29/01
HOSPITAL / HEALTH CENTER
RENOVATIONS
CONSTRUCTION DOCUMENT STIMATE
Project Area 25500 Square Feet
96 7800
CSI |
Description |
Total $ |
Percent |
Cost/SF |
||
|
01 |
General Requirements |
254,903 |
9.27% |
10.00 |
||
|
02 |
Site Work |
152,957 |
5.56% |
6.00 |
||
|
03 |
Concrete |
2,152 |
0.08% |
0.08 |
||
|
05 |
Metals |
42,204 |
1.53% |
1.66 |
||
|
06 |
Wood & Plastics |
101,296 |
3.68% |
3.97 |
||
|
07 |
Moisture-Thermal Control |
55,204 |
2.01% |
2.16 |
||
|
08 |
Doors, Windows & Glass |
120,130 |
4.37% |
4.71 |
||
|
09 |
Finishes |
294,724 |
10.71% |
11.56 |
||
|
10 |
Specialties |
30,163 |
1.10% |
1.18 |
||
|
11 |
Equipment |
17,335 |
0.63% |
0.68 |
||
|
15 |
Mechanical |
1,213,506 |
44.12% |
47.59 |
||
|
16 |
Electrical |
466,130 |
16.95% |
18.28 |
||
|
|
Job total |
|
$2,750,704 |
100.00% |
$107.87 |
|
|
|
Profit |
10% |
$275,070 |
|
|
|
|
|
Bond |
1% |
$27,507 |
|
|
|
|
|
Contingency |
10% |
$275,070 |
|
|
|
|
|
Grand Total |
|
$3,328,352 |
|
$130.52 |
|
|
||||||