03/29/01
OFFICE BUILDING
CONSTRUCTION DOCUMENT
Project Area 25493 Square Feet
97 1600
CSI |
Description |
Total $ |
Percent |
Cost/SF |
||
|
01 |
General Requirements |
197,374 |
5.84% |
7.74 |
||
|
02 |
Site Work |
501,738 |
14.85% |
19.68 |
||
|
03 |
Concrete |
290,105 |
8.58% |
11.38 |
||
|
04 |
Masonry |
246,849 |
7.30% |
9.68 |
||
|
05 |
Metals |
338,407 |
10.01% |
13.27 |
||
|
06 |
Wood & Plastics |
249,551 |
7.38% |
9.79 |
||
|
07 |
Moisture-Thermal Control |
166,566 |
4.93% |
6.53 |
||
|
08 |
Doors, Windows & Glass |
145,792 |
4.31% |
5.72 |
||
|
09 |
Finishes |
453,426 |
13.42% |
17.79 |
||
|
10 |
Specialties |
22,359 |
0.66% |
0.88 |
||
|
11 |
Equipment |
2,050 |
0.06% |
0.08 |
||
|
12 |
Furnishings |
9,854 |
0.29% |
0.39 |
||
|
13 |
Special Construction |
3,500 |
0.10% |
0.14 |
||
|
14 |
Conveying Systems |
51,000 |
1.51% |
2.00 |
||
|
15 |
Mechanical |
446,128 |
13.20% |
17.50 |
||
|
16 |
Electrical |
254,930 |
7.54% |
10.00 |
||
|
|
Job total |
|
$3,379,629 |
100.00% |
$132.57 |
|
|
|
Profit |
8% |
$270,370 |
|
|
|
|
|
Bond |
1% |
$33,796 |
|
|
|
|
|
Contingency |
5% |
$168,981 |
|
|
|
|
|
Grand Total |
|
$3,852,777 |
|
$151.13 |
|