03/29/01
BRANCH BANK
CONSTRUCTION DOCUMENT
Project Area 6960 Square Feet
95
3520
CSI |
Description |
Total $ |
Percent |
Cost/SF |
||
|
01 |
General Requirements |
34,608 |
6.15% |
4.97 |
||
|
02 |
Site Work |
32,007 |
5.69% |
4.60 |
||
|
03 |
Concrete |
5,546 |
0.99% |
0.80 |
||
|
04 |
Masonry |
60,249 |
10.70% |
8.66 |
||
|
05 |
Metals |
20,009 |
3.55% |
2.87 |
||
|
06 |
Wood & Plastics |
45,588 |
8.10% |
6.55 |
||
|
07 |
Moisture-Thermal Control |
15,910 |
2.83% |
2.29 |
||
|
08 |
Doors, Windows & Glass |
37,093 |
6.59% |
5.33 |
||
|
09 |
Finishes |
76,098 |
13.52% |
10.93 |
||
|
10 |
Specialties |
1,624 |
0.29% |
0.23 |
||
|
11 |
Equipment |
1,500 |
0.27% |
0.22 |
||
|
12 |
Furnishings |
5,758 |
1.02% |
0.83 |
||
|
15 |
Mechanical |
128,666 |
22.86% |
18.49 |
||
|
16 |
Electrical |
98,266 |
17.46% |
14.12 |
||
|
|
Job total |
|
$562,922 |
100.00% |
$80.88 |
|
|
|
Profit |
10% |
$56,292 |
|
|
|
|
|
Bond |
1% |
$5,629 |
|
|
|
|
|
Contingency |
5% |
$28,146 |
|
|
|
|
|
Grand Total |
|
$652,990 |
|
$93.82 |
|