03/29/01
DISTRIBUTION CENTER/WAREHOUSE
CONSTRUCTION DOCUMENT
Project Area 211961 Square Feet
92
0065
CSI
|
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
296,232 |
3.63 |
1.40 |
|
|
02 |
Site Work |
867,304 |
10.63 |
4.09 |
|
|
03 |
Concrete |
1,242,818 |
15.24 |
5.86 |
|
|
04 |
Masonry |
599,823 |
7.35 |
2.83 |
|
|
05 |
Metals |
1,290,695 |
15.82 |
6.09 |
|
|
06 |
Wood & Plastics |
43,142 |
0.53 |
0.20 |
|
|
07 |
Moisture-Thermal Control |
920,082 |
11.28 |
4.34 |
|
|
08 |
Doors, Windows & Glass |
120,226 |
1.47 |
0.57 |
|
|
09 |
Finishes |
336,992 |
4.13 |
1.59 |
|
|
10 |
Specialties |
7,598 |
0.09 |
0.04 |
|
|
14 |
Conveying Systems |
40,000 |
0.49 |
0.19 |
|
|
15 |
Mechanical |
1,096,967 |
13.45 |
5.18 |
|
|
16 |
Electrical |
1,295,082 |
15.88 |
6.11 |
|
|
|
Job total |
|
$8,156,960 |
100.00 % |
$38.48 |
|
|
Profit |
5% |
$407,848 |
|
|
|
|
Bond |
1% |
$81,570 |
|
|
|
|
Contingency |
0% |
$0 |
|
|
|
|
Grand Total |
|
$8,646,377 |
|
$40.79 |
|
|
|||||