03/29/01
POLICE HEADQUARTERS
100% CONSTRUCTION DOCUMENT
Project Area 45511 Square Feet
93 2620
CSI |
Description |
Total |
Percent |
Cost/SF |
||
|
01 |
General Requirements |
406,008 |
6.74% |
8.92 |
||
|
02 |
Site Work |
746,470 |
12.39% |
16.40 |
||
|
03 |
Concrete |
362,795 |
6.02% |
7.97 |
||
|
04 |
Masonry |
512,179 |
8.50% |
11.25 |
||
|
05 |
Metals |
257,216 |
4.27% |
5.65 |
||
|
06 |
Wood & Plastics |
126,900 |
2.11% |
2.79 |
||
|
07 |
Moisture-Thermal Control |
206,435 |
3.43% |
4.54 |
||
|
08 |
Doors, Windows & Glass |
421,219 |
6.99% |
9.26 |
||
|
09 |
Finishes |
573,779 |
9.53% |
12.61 |
||
|
10 |
Specialties |
127,160 |
2.11% |
2.79 |
||
|
11 |
Equipment |
126,977 |
2.11% |
2.79 |
||
|
13 |
Special Construction |
20,005 |
0.33% |
0.44 |
||
|
14 |
Conveying Systems |
128,000 |
2.13% |
2.81 |
||
|
15 |
Mechanical |
726,646 |
12.06% |
15.97 |
||
|
16 |
Electrical |
1,281,300 |
21.27% |
28.15 |
||
|
|
Job total |
|
$6,023,089 |
100.00% |
$132.34 |
|
|
|
Profit |
5% |
$301,154 |
|
|
|
|
|
Bond |
0.95% |
$57,219 |
|
|
|
|
|
Contingency |
5% |
$301,154 |
|
|
|
|
|
Grand Total |
|
$6,682,617 |
|
$146.84 |
|