03/29/01
FIRE STATION
60% CONSTRUCTION DOCUMENT
Project Area 6885 Square Feet
97 2810
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
31,200 |
4.12% |
4.53 |
|
|
02 |
Site Work |
45,766 |
6.04% |
6.65 |
|
|
03 |
Concrete |
60,383 |
7.97% |
8.77 |
|
|
04 |
Masonry |
156,423 |
20.64% |
22.72 |
|
|
05 |
Metals |
3,000 |
0.40% |
0.44 |
|
|
06 |
Wood & Plastics |
69,408 |
9.16% |
10.08 |
|
|
07 |
Moisture-Thermal Control |
52,364 |
6.91% |
7.61 |
|
|
08 |
Doors, Windows & Glass |
42,377 |
5.59% |
6.15 |
|
|
09 |
Finishes |
52,486 |
6.93% |
7.62 |
|
|
10 |
Specialties |
8,593 |
1.13% |
1.25 |
|
|
11 |
Equipment |
37,875 |
5.00% |
5.50 |
|
|
15 |
Mechanical |
85,501 |
11.28% |
12.42 |
|
|
16 |
Electrical |
112,449 |
14.84% |
16.33 |
|
|
|
Job total |
|
757,823 |
100.00% |
$110.07 |
|
|
Profit |
10% |
75,782 |
|
|
|
|
Bond |
1% |
7,578 |
|
|
|
|
Contingency |
10% |
75,782 |
|
|
|
|
Grand Total |
|
916,966 |
|
$133.18 |