03/29/01
PUBLIC WORKS FACILITY
DESIGN DEVELOPMENT ESTIMATE
Project Area 29377 Square Feet
00 0600
CSI |
Description |
Total |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
168,279 |
5.78% |
5.73 |
|
|
02 |
Site Work |
658,927 |
22.64% |
22.43 |
|
|
03 |
Concrete |
314,997 |
10.82% |
10.72 |
|
|
05 |
Metals |
62,729 |
2.16% |
2.14 |
|
|
06 |
Wood & Plastics |
55,189 |
1.90% |
1.88 |
|
|
07 |
Moisture-Thermal Control |
58,531 |
2.01% |
1.99 |
|
|
08 |
Doors, Windows & Glass |
167,298 |
5.75% |
5.69 |
|
|
09 |
Finishes |
155,474 |
5.34% |
5.29 |
|
|
10 |
Specialties |
35,049 |
1.20% |
1.19 |
|
|
12 |
Furnishings |
387 |
0.01% |
0.01 |
|
|
13 |
Special Construction |
436,028 |
14.98% |
14.84 |
|
|
15 |
Mechanical |
395,791 |
13.60% |
13.47 |
|
|
16 |
Electrical |
401,498 |
13.80% |
13.67 |
|
|
|
Job total |
|
$2,910,178 |
100.00% |
$99.06 |
|
|
Profit |
10% |
$291,018 |
|
|
|
|
Bond |
1% |
$29,102 |
|
|
|
|
Contingency |
5% |
$145,509 |
|
|
|
|
Grand Total |
|
$3,375,807 |
|
$114.91 |