03/29/01
TRAIN MAINTENANCE FACILITY
100% CONSTRUCTION DOCUMENT
Project Area 46691 Square Feet
97 2350
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
1,550,244 |
10.00% |
33.20 |
|
|
02 |
Site Work |
3,140,508 |
20.25% |
67.26 |
|
|
03 |
Concrete |
1,066,287 |
6.88% |
22.84 |
|
|
04 |
Masonry |
147,542 |
0.95% |
3.16 |
|
|
05 |
Metals |
401,247 |
2.59% |
8.59 |
|
|
06 |
Wood & Plastics |
51,367 |
0.33% |
1.10 |
|
|
07 |
Moisture-Thermal Control |
755,626 |
4.87% |
16.18 |
|
|
08 |
Doors, Windows & Glass |
115,145 |
0.74% |
2.47 |
|
|
09 |
Finishes |
174,168 |
1.12% |
3.73 |
|
|
10 |
Specialties |
33,511 |
0.22% |
0.72 |
|
|
11 |
Equipment |
4,152,310 |
26.77% |
88.93 |
|
|
14 |
Conveying Systems |
256,617 |
1.65% |
5.50 |
|
|
15 |
Mechanical |
1,150,017 |
7.42% |
24.63 |
|
|
16 |
Electrical |
2,514,366 |
16.21% |
53.85 |
|
|
|
Job total |
|
15,508,954 |
100.00% |
332.16 |
|
|
Profit |
10% |
1,550,895 |
|
|
|
|
Bond |
1% |
155,090 |
|
|
|
|
Contingency |
5% |
775,448 |
|
|
|
|
Grand Total |
|
17,990,387 |
|
385.31 |