03/29/01
TRAIN STATION
100%CONSTRUCTION DOCUMENT
Project Area 198304 Square Feet
98 1320
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
||||
|
01 |
General Requirements |
216,299 |
7.72% |
1.09 |
|
||||
|
02 |
Site Work |
1,494,857 |
53.32% |
7.54 |
|
||||
|
03 |
Concrete |
406,289 |
14.49% |
2.05 |
|
||||
|
04 |
Masonry |
24,190 |
0.86% |
0.12 |
|
||||
|
05 |
Metals |
114,460 |
4.08% |
0.58 |
|
||||
|
06 |
Wood & Plastics |
15,648 |
0.56% |
0.08 |
|
||||
|
07 |
Moisture-Thermal Control |
69,700 |
2.49% |
0.35 |
|
||||
|
08 |
Doors, Windows & Glass |
6,263 |
0.22% |
0.03 |
|
||||
|
09 |
Finishes |
50,694 |
1.81% |
0.26 |
|
||||
|
10 |
Specialties |
27,424 |
0.98% |
0.14 |
|
||||
|
13 |
Special Construction |
20,000 |
0.71% |
0.10 |
|
||||
|
15 |
Mechanical |
35,024 |
1.25% |
0.18 |
|
||||
|
16 |
Electrical |
322,674 |
11.51% |
1.63 |
|
||||
|
|
Job total |
|
$2,803,522 |
100.00% |
$14.14 |
|
|||
|
|
Profit |
10% |
$280,352 |
|
|
|
|||
|
|
Bond |
1% |
$28,035 |
|
|
|
|||
|
|
Contingency |
10% |
$280,352 |
|
|
|
|||
|
|
Grand Total |
|
$3,392,261 |
|
$17.11 |
|
|||