03/29/01
BUS FUEL AND SERVICE FACILITY
100% CONSTRUCTION DOCUMENT
Project Area 29472 Square Feet
94
3000
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
|
01 |
General Requirements |
570,953 |
8.29% |
19.37 |
|
|
02 |
Site Work |
1,085,382 |
15.76% |
36.83 |
|
|
03 |
Concrete |
205,161 |
2.98% |
6.96 |
|
|
04 |
Masonry |
531,845 |
7.72% |
18.05 |
|
|
05 |
Metals |
289,563 |
4.20% |
9.83 |
|
|
06 |
Wood & Plastics |
62,436 |
0.91% |
2.12 |
|
|
07 |
Moisture-Thermal Control |
351,293 |
5.10% |
11.92 |
|
|
08 |
Doors, Windows & Glass |
295,621 |
4.29% |
10.03 |
|
|
09 |
Finishes |
95,044 |
1.38% |
3.22 |
|
|
10 |
Specialties |
68,588 |
1.00% |
2.33 |
|
|
11 |
Equipment |
1,441,121 |
20.92% |
48.90 |
|
|
12 |
Furnishings |
4,450 |
0.06% |
0.15 |
|
|
13 |
Special Construction |
204,960 |
2.98% |
6.95 |
|
|
15 |
Mechanical |
799,238 |
11.60% |
27.12 |
|
|
16 |
Electrical |
881,737 |
12.80% |
29.92 |
|
|
|
Job total |
|
$6,887,392 |
100.00% |
233.69 |
|
|
Profit |
6.5% |
$447,680 |
|
|
|
|
Bond |
1% |
$68,874 |
|
|
|
|
Contingency |
3% |
$206,622 |
|
|
|
|
Grand Total |
|
$7,610,568 |
|