03/29/01
VEHICLE MAINTENANCE BUILDING
90% CONSTRUCTION DOCUMENT
Project Area 8748 Square Feet
99 1100
CSI |
Description |
Total $ |
Percent |
Cost/SF |
|
||||||
|
01 |
General Requirements |
45,542 |
4.23% |
5.21 |
|
||||||
|
02 |
Site Work |
25,845 |
2.40% |
2.95 |
|
||||||
|
03 |
Concrete |
88,947 |
8.27% |
10.17 |
|
||||||
|
04 |
Masonry |
132,438 |
12.32% |
15.14 |
|
||||||
|
05 |
Metals |
87,228 |
8.11% |
9.97 |
|
||||||
|
06 |
Wood & Plastics |
36,492 |
3.39% |
4.17 |
|
||||||
|
07 |
Moisture-Thermal Control |
44,197 |
4.11% |
5.05 |
|
||||||
|
08 |
Doors, Windows & Glass |
61,372 |
5.71% |
7.02 |
|
||||||
|
09 |
Finishes |
104,792 |
9.74% |
11.98 |
|
||||||
|
10 |
Specialties |
12,590 |
1.17% |
1.44 |
|
||||||
|
11 |
Equipment |
91,400 |
8.50% |
10.45 |
|
||||||
|
12 |
Furnishings |
1,813 |
0.17% |
0.21 |
|
||||||
|
15 |
Mechanical |
191,056 |
17.77% |
21.84 |
|
||||||
|
16 |
Electrical |
151,698 |
14.11% |
17.34 |
|
||||||
|
|
Job total |
|
$1,075,412 |
100.00% |
$122.93 |
|
|||||
|
|
Profit |
10% |
$107,541 |
|
|
|
|||||
|
|
Bond |
1% |
$10,754 |
|
|
|
|||||
|
|
Contingency |
5% |
$53,771 |
|
|
|
|||||
|
|
Grand Total |
|
$1,247,478 |
|
$142.60 |
|
|||||
|
|
|
|
|
|
|||||||